On this blog you can find updates on the process of moving to the new Digital Hub office. From now on you can expect monthly status updates. Shared files will be password protected. You received the password via email, please don't share it outside your company. As a test you can view our newest team photo here.


 

Current state - 07/22


Due to delays on the construction site, the floors 1-3 won't be finished before the first of December. That is why the move of the Hub will be split into two parts. The first part will take place in October to get the 4th and 5th floor ready for the HubDay on the 8th of November.





The Startups will be able to start moving to the new building either in the middle of December or in January - depending on the progress of the construction site.